İSKİ Wastewater Tunnel Construction (Ayazağa–Kemerburgaz)

A major environmental engineering project that collects municipal wastewater from the Ayazağa, Göktürk and Kemerburgaz catchments and conveys it to the Baltalimanı Advanced Biological Wastewater Treatment Plant through gravity and pressure tunnels. The 8,338-metre main tunnel, with a 3,000 mm internal diameter, was completed beneath built-up areas using an EPB closed-face TBM without surface deformation. Designed for a flow capacity of 332,650 m³ per day, it will serve a population of 746,000 for 100 years.

Engineering Scope & Project Story

A major environmental engineering project that collects municipal wastewater from the Ayazağa, Göktürk and Kemerburgaz catchments and conveys it to the Baltalimanı Advanced Biological Wastewater Treatment Plant through gravity and pressure tunnels. The 8,338-metre main tunnel, with a 3,000 mm internal diameter, was completed beneath built-up areas using an EPB closed-face TBM without surface deformation. Designed for a flow capacity of 332,650 m³ per day, it will serve a population of 746,000 for 100 years.

Advanced Safety & Occupational Health

A zero-accident policy aligned with ISO 45001 and continuous gas-monitoring systems.

Modern Technology

Laser-guided TBM steering, hydraulic injection and high-strength reinforced-concrete solutions.

Environment & Sustainability

Zero-settlement excavation methods that protect groundwater conditions and the urban fabric.

Contract & Technical Parameters

Employer / Authority
İSKİ General Directorate
Project Location
Istanbul, Türkiye
Sector
Infrastructure
Contract Model
Design-Build, Turnkey
Project Status
Ongoing Project